Case study · Electrical & containment

Enquiry to site in 72 hours

Vic Coupland Ltd needed a faster, simpler way to suspend multiple services in a Hull paddle court and sports centre. A Zip-Strut solution was designed on site, quoted the same day and delivered in under 3 days.

Installed by Vic Coupland LtdDistributed by Edmundson Electrical, HullZip-Strut · Con-Lock · Loop-It
Cable tray and cable basket suspended on Zip-Clip wire and Zip-Strut inside the Hull sports centre

Cable tray and basket suspended on Zip-Strut, Hull

<72hEnquiry to stock on site
<1hrQuote to purchase order
Up to 5 tiers800mm Zip-Strut runs
50%Cut install time in half (installer’s estimate)

The customer

A major Hull contractor, new to Zip-Strut

Vic Coupland Ltd is one of the larger contractors in Hull. Zip-Clip have worked with them before on the HVAC side, but this was their first Zip-Clip electrical project and their first order of Zip-Strut. The order came through Edmundson Electrical in Hull, with Craig Harman, Assistant Branch Manager, as our contact.

Cable tray and stacked Zip-Strut suspended on wire at the Hull sports centre
Cable tray corner runs suspended on Zip-Strut

The challenge

An over-specified design and a supplier that let them down

The enquiry arrived from Edmundson Electrical, Hull, on 18 August with a design from a competitor that looked heavily over-specified and expensive. That supplier had already let the contractor down on lead time and service, so the distributor asked whether Zip-Clip could help.

The site added its own limits. Several services ran side by side, drilling and looping around the beams and purlins wasn’t possible, and a fire wall had already been installed down the middle partition and ceiling.

The Zip-Clip solution

Designed on site, with the team on FaceTime

The next morning, 19 August, our North East Regional Sales Manager, Gemma, walked the site with Mark, Director at Vic Coupland. With James Horton, our R&D Commercial Director, on FaceTime, we designed the whole job there and then. For the services running side by side we specified two-tier, multi-stacked Zip-Strut in 800mm lengths.

Paddle court

Most services suspended by loops around the existing Unistrut.

Upstairs gym

Suspended using Con-Lock anchors, with no beam fixings needed.

Fire wall

Wire wasn’t an option, so we suggested cantilevering from the wall instead.

The timeline

Quote in under an hour, stock on site in days

18 Aug

Enquiry received from Edmundson Electrical

19 Aug

Site visit, on-site design, quotation and drawings issued, purchase order raised

21 Aug

First half of the order delivered to site

27 Aug

Pull test on the CLS Con-Lock anchors

24 Sep

Follow-up visit to the finished install

“Easy half the time if not more.”

Installer at Vic Coupland, comparing the double-stacked Zip-Strut section with a double-stacked cantilever install

The result

A great install, and installers who couldn’t praise it enough

Back on site on 24 September, the install was excellent. The installers had done a really good job, and their feedback was consistent.

Quick and simple

“Zip-Strut installation was so quick and simple.”

Time saving

“Massive time saving.”

Easy to use

“Easy and great to work with.”

Game changer

“Game changer on install.”

Watch

See the install in action

On site

The finished install

Five tiers of Zip-Strut suspended on wire above cable tray and basket at the Hull sports centre
Cable tray suspended on Zip-Strut and wire across the ceiling at the Hull sports centre
Cable tray and basket suspended on Zip-Strut above a site visitor inspecting the install

Design assistance

Got a tricky install?

Tight space, low ceiling void, long drop or a heavy load? Send us your project and we’ll build you a solution, supplied through your local wholesaler.